Puerto Rico’s Energy Bureau (NEPR) issued a Resolution and Order requiring Genera to show cause why it should not face administrative penalties for missing the deadline to complete a 268-megawatt “peaker” backup generation project.
The Resolution gives Genera 20 days to respond and request an adjudicative hearing if it chooses to. The project was originally authorized in 2023, and the Bureau later allowed Genera to take over the procurement process after the company represented that it could complete it faster, more cheaply and more efficiently. After reviewing reports submitted by the company, however, NEPR had previously concluded that the project had significantly deviated from its original cost and schedule projections, and in September 2024 ordered that the work be completed no later than the end of the second quarter of 2026. That determination was later upheld by the Court of Appeals.
The Resolution states that monthly reports submitted by Genera after June 2026 show the project was not completed within the established deadline. The company attributed the delay to factors related to permitting, coordination with LUMA Energy, matters tied to FEMA, interconnection requirements and other elements it said were outside its control — but the Bureau concluded those explanations alone do not relieve a regulated entity from complying with a valid order.




